August 20, 2013 City Council Meeting

August 20, 2013 Stillwater, OK
Watch Video
Subscribe

Get notified when new summaries are available.

Meeting Summary

TL;DR

The Stillwater City Council held its August 19, 2013 meeting, where they approved several resolutions, including calling for an election on November 12th for general obligation bonds for Parks and Recreation and Public Safety initiatives, and a sales tax authorization for transportation. They also adopted revisions to design and construction standards and discussed the Marketplace Fairness Act and tax-exempt municipal financing. The Stillwater Utility Authority also met, approving a consent docket and discussing the development of a new electric power generation station and reviewing the completion of 18 American Recovery and Reinvestment Act (ARRA) projects.

Key Decisions & Votes

Consent Docket (City Council)

01:00

The consent docket was approved with the removal of item C.

Approved

Closure of Utility Easements

07:00

The council approved the request to close utility easements at 711 West Peaceable Acres Road for the development of a retirement community.

Approved

Revisions to Design and Construction Standards

10:00

Minor revisions to transportation details and a change to lid materials for AMR system compatibility were approved.

Approved

Resolution Adopting Revisions to Design and Construction Standards

14:00

Resolution 2013-13, formally adopting the previously approved revisions to the design and construction standards, was adopted.

Adopted

Resolution of Support for HR 684 (Marketplace Fairness)

16:00

Resolution 2013-14, supporting the Marketplace Fairness Act to ensure sales tax collection on internet purchases, was adopted.

Adopted

Resolution on Preservation of Tax Exempt Municipal Financing

19:00

Resolution 2013-14, conveying a municipal position on preserving tax-exempt municipal financing, was adopted.

Adopted

Resolution Calling Election for Parks & Recreation and Public Safety Bonds

21:00

Resolution 2013-15, calling for an election on November 12th for general obligation bonds not to exceed $20 million for Parks and Recreation and $7.5 million for Public Safety, was adopted.

Adopted

Resolution for Transportation Sales Tax Authorization

26:00

Resolution 2013-16, proposing adoption of Ordinance 3237 to amend the municipal code for a 1% transportation sales tax, was adopted.

Adopted

Ordinance 3237 (Transportation Sales Tax) - First Reading

29:00

The first reading of Ordinance 3237, concerning the 1% transportation sales tax, was approved.

Approved

Ordinance 3236 (Land Development Code Amendment) - Second Reading

31:00

The second reading of Ordinance 3236, amending the Land Development Code regarding industrial districts, was approved.

Approved

Consent Docket (Utility Authority)

35:00

The Stillwater Utility Authority's consent docket was approved.

Approved

Power Generation Station Development (Utility Authority)

36:00

The Utility Authority authorized the general manager to enter into a professional services agreement for engineering design, complete a land swap, and prepare a bond offering for a proposed electric power generation station.

Approved

Upcoming Community Events

September 24th

National Voter Registration Day

The Stillwater League of Women Voters will set up stations at City Hall and other locations for voter registration, address changes, and information on voter ID, absentee ballots, and upcoming resolutions.

Financial Matters

Utility Payment Taxation

A public commenter stated that 31.4% of a typical Stillwater utility payment is taxation, not voted on by citizens, and used for general city funds.

General Obligation Bonds (Parks & Recreation)

Proposed bond issuance for a baseball/softball/soccer facility, outdoor amphitheater, boardwalk, and lakefront development at Boomer Lake Park.

$20,000,000

General Obligation Bonds (Public Safety)

Proposed bond issuance for a new fire station, fire engine, police vehicles, video equipment for vehicles, and public safety communications system upgrades.

$7,500,000

Transportation Sales Tax

Proposed sales tax to replace the existing half-cent sales tax, providing for transportation projects and bond obligations.

1%

Power Generation Station Engineering Services

Authorization for expenditures up to $4.5 million for engineering design and bidding services for a new power generation station.

$4,500,000

ARRA Projects Funding

Total cost of 18 ARRA water and wastewater improvement projects. The total ARRA loan amount was $13,410,286.25, with $2,578,998.81 forgiven. The SUA contributed $246,102.57.

$13,656,388.82

Public Comments

2 citizens spoke

Two citizens addressed the council. One expressed concern over the city's reliance on utility payment taxation, while the other spoke in favor of the upcoming election resolution and requested support for voter education.

Utility taxation Voter education Upcoming election

Coming Up

Deadlines

  • September 24th: National Voter Registration Day
  • November 12th: Election for Parks & Recreation and Public Safety bonds and Transportation Sales Tax

Watch For

  • Public meetings and information on the 'Our Stillwater' initiatives
  • Stillwater Utility Authority to return in approximately 60 days with more information on the power generation station development
  • Formal approval of land swap for power generation station in October

Announcements

  • City staff will provide information sheets and packets, and hold public meetings regarding the 'Our Stillwater' initiatives to educate voters.
  • The Stillwater Utility Authority recognized city staff for their successful completion of 18 ARRA water and wastewater improvement projects, including the AMR system installation.

Agenda Summary

Consent Docket

Approval of routine administrative items.

Approved (except item C)

Public Comment Not Scheduled for Public Hearing

Opportunity for citizens to address the council on non-agenda items.

Information Only

Closure of Utility Easements at 711 West Peaceable Acres Road

Request to close three utility easements for the development of a retirement community.

Approved

Revisions to Stillwater Design and Construction Standards

Minor corrections to transportation details and changes to lid materials for AMR system compatibility.

Approved

Resolution 2013-13: Adopting Revisions to Stillwater Design and Construction Standards

Formal adoption of the previously discussed revisions to design and construction standards.

Adopted

Resolution 2013-14: Support for HR 684 (Marketplace Fairness)

Resolution supporting federal legislation to ensure sales tax collection on internet purchases.

Adopted

Resolution 2013-14: Conveying Municipal Position on Preservation of Tax Exempt Municipal Financing

Resolution opposing the removal of tax exemption on municipal bonds.

Adopted

Resolution 2013-15: Calling Election for Parks & Recreation and Public Safety General Obligation Bonds

Resolution to hold an election on November 12th for general obligation bonds for Parks & Recreation ($20M) and Public Safety ($7.5M) initiatives.

Adopted

Resolution 2013-16: Proposing Adoption of Ordinance 3237 (Transportation Sales Tax)

Resolution to propose an ordinance amending the municipal code to create a 1% transportation sales tax.

Adopted

Ordinance 3237: 2013 Transportation Sales Tax Ordinance (First Reading)

First reading of the ordinance to levy a 1% transportation sales tax.

Approved

Ordinance 3236: Amending Chapter 23 Land Development Code (Second Reading)

Second reading of an ordinance amending the Land Development Code regarding industrial districts.

Approved

Reports from Officers and Boards

Updates and information from city officials and board representatives.

Information Only

Consent Docket (Stillwater Utility Authority)

Approval of routine administrative items for the Utility Authority.

Approved

Power Generation Station Development

Discussion and authorization for next steps in developing a new electric power generation station, including engineering, land acquisition, and financing.

Approved

ARRA Completion Summary

Presentation and wrap-up report on the completion of 18 American Recovery and Reinvestment Act (ARRA) water and wastewater improvement projects.

Information Only