The Stillwater City Council addressed several key issues, including the postponement of two public hearings related to rezoning requests, the approval of a grant application for COVID-19 rental and utility assistance, and a significant accessibility improvement project for the Stillwater Community Center. The council also approved several budget amendments and discussed a new investment policy and airport parking district.

Key Decisions & Votes

Postponement of Rezoning Request (908 East 12th Avenue)

07:00

The public hearing for a map amendment to rezone property at 908 East 12th Avenue was postponed to January 25, 2021, at the applicant's request for additional time to gather input from homeowners.

Postponed

Postponement of Rezoning Request (4814 North Washington Street)

07:50

A public hearing for a map amendment at 4814 North Washington Street was postponed to March 1, 2021, with a requirement for new public notice to be published. This was due to concerns about the process and the need for all parties to be present.

Postponed

Application for CDBG Coronavirus Response Program Grant

20:00

The council approved a resolution to apply for a $490,000 Community Development Block Grant Coronavirus Response Program (CDBG-CV) for rent and utility assistance, targeting extremely low-income individuals.

Approved

Stillwater Community Center Accessibility Project

37:00

The council approved moving forward with detailed planning for an accessibility improvement project at the Stillwater Community Center, including a ramp and stair system, and affirmed the city's commitment to provide up to $40,000 in in-kind electrical work.

Approved

Sixth Avenue Corridor Study Agreement

57:00

An agreement with Confluence for a Sixth Avenue Corridor Study, not to exceed $100,000, was approved. This study will focus on urban design, land use, and transportation issues adjacent to the Sixth Street ODOT project.

Approved

Stillwater Regional Airport Security and Compliance Coordinator Salary

01:06:00

A budget amendment was approved to allocate CARES Act funds for the FY2020 salary of the Security and Compliance Coordinator position at the Stillwater Regional Airport.

Approved

Master Park and Community Resources Plan

01:09:00

A budget amendment transferring $185,000 from capital funds to create a Master Park and Community Resources Plan was approved, and staff was authorized to release an RFP for the plan.

Approved

Pavement Management Program Full Depth Repair Bid

01:20:00

The bid for full depth pavement replacement was awarded to Gelino CCC, with authorization for other city departments to use the contract for their projects.

Approved

Perkins Road Reconstruction Project Amendment

01:24:00

Amendments to the professional services contract with Olsson Associates for the Perkins Road reconstruction project were approved, allocating an additional $60,000 for design work and geotechnical studies.

Approved

Western Airport Arterial Extension Amendment

01:29:00

Amendment 2 to the professional services agreement with Olsson Associates was approved for the Western Airport Arterial extension, allocating up to $40,000 for environmental clearance related to ball field relocation.

Approved

Community Power Coats for the Community Program

01:34:00

A budget amendment allocating $10,000 from the Grand River Dam Authority to fund the Community Power Coats for the Community program was approved.

Approved

Stillwater City Investment Policy Update

01:36:00

Resolution CC-2021-2, adopting an updated investment policy for the City of Stillwater and its trusts, was adopted. The policy includes provisions for professional investment consultants and increased limits on funds in single financial institutions.

Adopted

Stillwater Regional Airport Parking District

01:42:00

Resolution CC-2021-3, establishing a parking district at the Stillwater Regional Airport, was adopted to allow for better management and enforcement of parking regulations.

Adopted

Ordinance 3468 (Utility Easement Closure)

01:43:00

Ordinance 3468, closing a portion of a utility easement at 5020 North Washington Street, was advanced to its second reading.

Advanced to Second Reading

Ordinance 3469 (Motor Vehicles and Traffic Amendments)

01:44:00

Ordinance 3469, amending Chapter 29 of the city code regarding motor vehicles and traffic to support the new airport parking district, was advanced to its second reading.

Advanced to Second Reading

Ordinance 3467 (Rezoning North Jefferson Street/West McElroy Road)

01:46:00

Ordinance 3467, rezoning properties at 815, 817, and 823 North Jefferson Street and 924 West McElroy Road from RT to RTM (family residential to family and multi-family residential), was adopted.

Adopted

Stillwater Medical Center Board Appointments

01:47:00

Joe Haney and Beth Buchanan were reappointed, and Gary Clark was appointed as a new member to the Stillwater Medical Center Board.

Approved

City Hall Transfer Switch Project

01:57:00

The City Hall transfer switch project, with expenditures up to $169,000, was approved to minimize power outages and surges by providing redundant service from another substation.

Approved

Waste Management Polycart Purchase and Contingency Fund Transfer

02:00:00

Release of $200,000 in previously allocated grant match funds was approved, with $60,000 appropriated to the waste management operational fund for residential polycart purchases and $140,000 transferred to the waste management contingency fund.

Approved

Upcoming Community Events

January 18

Martin Luther King Jr. Day Celebration

Hosted by Stillwater Community United, a relay march around town starting at Southern Woods Park with 15 stops, concluding with an outdoor speech at the university. Begins at 12:30 PM.

Financial Matters

CDBG Coronavirus Response Program Grant Application

Application for federal funds for rent and utility assistance for extremely low-income individuals.

$490,000

Stillwater Community Center Accessibility Project (City Contribution)

In-kind contribution for electrical work related to the accessibility improvements.

$40,000

Sixth Avenue Corridor Study

Funding for a comprehensive study of the Sixth Avenue corridor, reallocated from the Duck Street project.

$100,000

Stillwater Regional Airport Security and Compliance Coordinator Salary

Allocation of CARES Act funds for the FY2020 salary of the position.

Master Park and Community Resources Plan

Transfer of capital funds to finance the development of a master plan for parks and community resources.

$185,000

Perkins Road Reconstruction Project Amendment

Additional funds from the sales tax for design work and geotechnical studies.

$60,000

Western Airport Arterial Extension Amendment

Expenditures from project reserve for environmental clearance related to ball field relocation.

$40,000

Community Power Coats for the Community Program

Grant funds received from Grand River Dam Authority for purchasing coats, hats, and gloves for those in need.

$10,000

City Hall Transfer Switch Project

Expenditures from the electric rate stabilization fund for infrastructure improvements at City Hall.

$169,000

Waste Management Polycart Purchase and Contingency Fund Transfer

Release of previously allocated grant match funds, with $60,000 for polycart purchases and $140,000 to the contingency fund.

$200,000

Public Comments

1 citizen spoke

One resident expressed disappointment and confusion regarding the development application process, specifically concerning the splitting and repeated tabling of rezoning and special use permit requests. She requested the city revisit and clarify the process for citizens.

Development application process Rezoning issues Special Use Permits (SUP) Public hearing transparency

Coming Up

Tabled

  • Public hearing for rezoning at 908 East 12th Avenue (rescheduled to January 25, 2021)
  • Public hearing for rezoning at 4814 North Washington Street (rescheduled to March 1, 2021)

Deadlines

  • Voter registration deadline for City Council election (January 15th)
  • Absentee ballot request deadline for City Council election (February 2nd)
  • CDBG Coronavirus Response Program grant application (February 1st)

Watch For

  • More detailed plans for the Stillwater Community Center accessibility project
  • Public input process for the Sixth Avenue Corridor Study
  • Public involvement process for ODOT's Sixth Street engineering design
  • Future discussions on continuing other funding for rental/mortgage assistance

Announcements

  • Waste Management, Water Utilities, and Public Works crews recognized for ice storm debris collection (65% complete, 3.56 million pounds collected).
  • Stillwater City Council election for Seat 4 is approaching; voter registration deadline is January 15th, absentee ballot request deadline is February 2nd, election day is February 9th.
  • Danny Wick Excavating completed the Hunters Ridge water line project, improving resiliency and water quality.
  • City Hall will be closed on Monday, January 18th, for Martin Luther King Jr. Day. Trash and recycling will be collected as usual, but not yard waste.
  • Rural fire service contracts are available for residents outside city limits for $100, ensuring emergency response fees do not exceed $2,000.
  • Vacancy on the Board of Adjustment for an unexpired seat (three-year term); applications available at stillwater.org/citizenboards.

Agenda Summary

Public Comment on items not scheduled for public hearings

Resident Michelle Magalossi spoke about concerns regarding the development application process, specifically the handling of rezoning and special use permit requests.

Information Only

6A: Public Hearing - Map Amendment to Rezone Property (908 East 12th Avenue)

Request for a map amendment to rezone property at 908 East 12th Avenue.

Postponed

6B: Public Hearing - Map Amendment to Rezone Property (4814 North Washington Street)

Request for a map amendment to rezone property at 4814 North Washington Street.

Postponed

6C: Public Hearing - Oklahoma Department of Commerce Community Development Block Grant Coronavirus Response Program (CC-21-10)

Public comment on the application for a CDBG-CV grant for rental and utility assistance.

Information Only

7A: Presentation Proposal from Stillwater Community Center Foundation

Proposal to provide accessible parking and a ramp/stair system on the south side of the Community Center.

Approved

7B: Approve Entering into an Agreement with Confluence for the Sixth Avenue Corridor Study

Agreement for a study on urban design, land use, and transportation issues related to the Sixth Street corridor.

Approved

7C: Approved Budget Amendments Allocating CARES Act Funding for FY2020 Salary of Security and Compliance Coordinator at Stillwater Regional Airport

Budget amendment to cover the salary of the airport's Security and Compliance Coordinator using CARES Act funds.

Approved

7D: Approved Budget Amendment Transferring $185,000 from FY21 Capital Fund to Master Park and Community Resources Plan Fund

Budget amendment to fund a master plan for parks and community resources and authorize an RFP.

Approved

7E: Bid Recommendation for the Fiscal Year 20 Pavement Management Program Full Depth Repair

Recommendation to award the bid for full depth pavement repair.

Approved

7F: Approve Amendments to the Professional Services Contract with Olsson Associates (Perkins Road Reconstruction)

Amendments to the contract for the Perkins Road reconstruction project to cover additional design and geotechnical work.

Approved

7G: Approve Amendment 2 to Professional Services Agreement with Olsson Associates (Western Airport Arterial Extension)

Amendment to the agreement for the Western Airport Arterial extension to cover environmental clearance for ball field relocation.

Approved

7H: Approved Budget Amendment Allocating Grant Funds Received from Grand River Dam Authority

Budget amendment for funds to support the Community Power Coats for the Community program.

Approved

7I: Overview of Updated City of Stillwater Investment Policy

Presentation and discussion of a revised investment policy for the city.

Information Only

7J: Overview of Proposed Parking District at Stillwater Regional Airport

Presentation and discussion of a proposed parking district at the airport.

Information Only

8A: Resolution CC-2021-1 (CDBG Coronavirus Response Program)

Resolution regarding the application for the CDBG Coronavirus Response Program grant.

Adopted

8B: Resolution CC-2021-2 (Investment Policy)

Resolution adopting an updated investment policy for the City of Stillwater.

Adopted

8C: Resolution CC-2021-3 (Stillwater Regional Airport Parking District)

Resolution establishing a parking district at the Stillwater Regional Airport.

Adopted

9A: Ordinance 3468 (Utility Easement Closure)

Ordinance closing a portion of a utility easement at 5020 North Washington Street.

Advanced to Second Reading

9B: Ordinance 3469 (Motor Vehicles and Traffic Amendments)

Ordinance amending city code regarding motor vehicles and traffic to support the airport parking district.

Advanced to Second Reading

9C: Ordinance 3467 (Rezoning North Jefferson Street/West McElroy Road)

Ordinance rezoning properties at 815, 817, and 823 North Jefferson Street and 924 West McElroy Road.

Adopted

12: Appointments

Appointments to the Stillwater Medical Center Board.

Approved

5A: Approved City Hall Transfer Switch Project and Budget Amendment

Project to install an automated transfer switch at City Hall to improve power reliability.

Approved

5B: Approved Release of Previously Allocated Grant Match Funds

Release of funds for waste management, including polycart purchases and transfer to contingency.

Approved