Meeting Summary
The city council held a study session to review the status of the FYE 2023 Capital Improvements Program (CIP) budget and prepare for the FYE 2024 CIP budget. An extensive discussion also took place regarding a resolution to appropriate $1,139,088 from the seizures and restitution fund for Public Safety Equipment. Council reached a consensus to split the public safety equipment funding into two separate resolutions for a future vote, one for general equipment and one for the armored rescue vehicle and its training.
Key Decisions & Votes
Public Safety Equipment Funding Resolution Structure
02:00:00Council reached a consensus to split the proposed resolution for Public Safety Equipment funding into two separate resolutions for a future vote. One resolution will cover all general public safety equipment, to be funded by seizure funds. The second resolution will specifically address the armored rescue vehicle and its associated training, with the general fund proposed as a funding option for amendment.
Upcoming Community Events
Young Family Athletic Center Topping Out
12 o'clock luncheon
Financial Matters
FYE 2023 Capital Improvements Program Budget
Total budget for 451 capital projects.
Capital Sales Tax Allocation Guidelines
Guidelines for allocating new capital sales tax revenue: 36% for other projects/debt service, 27% for Capital company, 25% for Street Maintenance, 7% contingency, 5% for maintenance of existing facilities.
Vehicle Replacement Program (FYE 23)
Funds spent to replace 16 units.
Recurring Sidewalk Projects (FYE 23)
Includes schools and arterials, sidewalk accessibility, city-wide sidewalks, downtown area sidewalks, sidewalks and trails, and horizontal saw cut program.
Other Recurring Projects (FYE 23)
Includes Capital outlay, Street Maintenance, Maintenance of existing facilities, Stormwater drainage maintenance, ODOT audit adjustments, ADA compliance and repair, Bridge maintenance, Driveway repairs, Street striping, Traffic calming, Community neighborhood improvements, Building Maintenance, and GIS mapping update.
Emergency Communications and Operations Center (PSST Fund)
Construction project, 19,800 sq ft, fully hardened, operational redundancies, ECC, EOC, incident command, traffic management center, IT spaces.
Fire Apparatus Replacement (PSST Fund, FYE 24)
Last year of replacement, includes new aerial platform and staff/support vehicles.
Young Family Athletic Center (Norman Forward)
135,000 sq ft facility with basketball/volleyball courts, competition/recreational pools, health systems clinic, retail/restaurant space.
Senior Wellness Center (Norman Forward)
30,000 sq ft facility with arts/crafts, indoor walking track, workout areas, fitness classroom, game room, lounge, outdoor patio, multi-use area, stage, wellness rooms, kitchen, coffee bar.
Reeves Park Improvement Project (Norman Forward)
Phase one of master plan, relocated park maintenance, road loop, parking, t-ball fourplex, LED field lights, restroom, concession, covered bleachers, detention pond, enhanced walks, trees, vendor areas, improvements to existing fields.
Griffin Park Project (Norman Forward)
Phases one through five complete, phase six underway. Converted remaining field space to soccer fields with new lights, parking, concession, restrooms.
Public Safety Equipment (Seizure Funds)
Proposed appropriation for various public safety equipment for SWAT, HDU, and general use.
Coming Up
Deadlines
- CIP: February 14th - Discuss proposed new projects and midpoint evaluations
- CIP: May 2nd - Review final proposed plan for FYE 2024
- Public Safety Study RFP: Due out in December
- OTA Turnpike Hearing: End of November
Watch For
- Bridge Bond program to return to full Council in January
- Stormwater master plan update
- Fire Station 5 reconstruction (funded when current bonds are paid off, approximately 3 years)
- Public Safety Equipment resolutions to be agendized for a future meeting
- ODOT looking at Highway 9 urban section realignment and widening
Agenda Summary
Discussion regarding the status of the FYE 2023 Capital Improvements program budget and preparation of the FYE 2024 Capital Improvement program budget
Presentation and discussion on the current status of capital projects, funding sources, and upcoming plans for FYE 2024 and the 2025-2028 Capital Improvements Plan. Included updates on significant completed, underway, and under construction projects, as well as recurring projects and future plan updates.
Resolution appropriating one million one hundred thirty-nine thousand and eighty-eight dollars from the seizures and restitution fund to balance for the purchase of certain Public Safety Equipment to be used during special events critical incidents search and rescue events and safety equipment for the SWAT team and hazardous devices unit
Detailed presentation and discussion on the need for various public safety equipment, including negotiation equipment, training kits, ballistic shielding, respirators, breaching equipment, large venue security, night vision, aiming laser systems, an armored rescue vehicle, hazardous device unit equipment (vests, helmets, bomb suits, x-ray, radiation detector, tools, robots), unmanned aerial systems, and electric assist bikes. The funding source (seizure funds) and the armored vehicle were points of extensive discussion.