Meeting Summary

TL;DR

The city council held a study session to discuss the final proposed Capital Improvements Program (CIP) budget for fiscal year ending 2024, along with the Capital Improvements Plan for FY25-28. Key discussions included changes in capital sales tax allocations, specific project funding, and challenges related to public safety apparatus replacement and infrastructure needs.

Key Decisions & Votes

Capital Sales Tax Allocation Shift

Not specified

The allocation for maintenance of existing facilities was increased from 5% to 7% of capital sales tax revenue, while general contingency was decreased from 7% to 5% for FY2024, to better address expanding facility maintenance needs.

Adopted in Proposed Budget

Aerial Ladder Platform Request

Not specified

A request for a $2.1 million aerial ladder platform for the fire department was denied in the proposed FY2024 budget due to insufficient funds within the apparatus replacement program. Options for funding will be discussed by the finance committee.

Denied in Proposed Budget

ADA Compliance Program

Not specified

Staff recommended including a $300,000 amendment for the recurring ADA compliance program in the FYE 24 budget to maintain the 2018 ADA transition plan.

Recommended for Amendment

Regional Transit Authority (RTA) Funding

Not specified

The RTA's funding request was increased from $182,000 to $348,000 in the proposed FYE 24 budget, partly due to other cities withdrawing and increased project activity.

Increased in Proposed Budget

Norman Ford Fund Re-appropriation

Not specified

Funds were de-appropriated from the current fiscal year and re-appropriated for the Young Family Athletic Center and Adult Wellness Center in FYE 24 to ensure a positive ending fund balance.

Action Taken in Proposed Budget

Reeves Park Maintenance Building

Not specified

Phase one of the Reeves Park Maintenance building was included in the proposed budget to improve efficiency for maintaining baseball and softball fields and to replace an old, crumbling maintenance building.

Included in Proposed Budget

Financial Matters

Public Safety Sales Tax Fund - Aerial Ladder Platform

Request for a $2.1 million aerial ladder platform for the fire department, which was denied in the proposed budget due to insufficient funds within the apparatus replacement program.

$2,100,000

CDBG Fund - Habitat Acquisition

New capital project for affordable housing land acquisition.

$40,000

CDBG Fund - NHA Land Acquisition

New capital project for affordable housing land acquisition.

Room Tax Fund - Westwood Tennis Center Improvements

Capital project scheduled for FYE 24.

$150,000

Room Tax Fund - Westwood Park Master Plan

Capital project scheduled for FYE 24.

$25,000

Capital Fund - Recurring Sidewalk Projects

Includes sidewalk programs for schools/arterials, accessibility, Citywide 50/50 matching, downtown area, sidewalks and trails, and horizontal saw cut program.

$420,000

Capital Fund - Street Maintenance

Includes Alex Fair asphalt pavement maintenance, concrete pavement maintenance, and crack seal programs.

Capital Fund - Maintenance of Existing Facilities

Allocation changed from 5% to 7% of capital sales tax revenue for FYE 24.

Capital Fund - Stormwater Drainage Maintenance Projects

Recurring capital project.

Capital Fund - Personnel Costs

Recurring capital project.

Capital Fund - ODOT Audit Adjustments

Account to cover unexpected bills from old ODOT completed projects.

$100,000

Capital Fund - Bridge Maintenance

Recurring capital project.

Capital Fund - Driveway Repairs

Recurring capital project.

Capital Fund - Street Striping

Recurring capital project.

Capital Fund - Traffic Calming

Recurring capital project.

Capital Fund - Community and Neighborhood Improvements

Infrastructure project located in CDBG target areas.

Capital Fund - ADA Compliance Program

Staff recommended amendment for a recurring project to maintain the 2018 ADA transition plan.

$300,000

Capital Fund - Monument Signs Project

Project to begin identifying locations for monument signs at major entrances to Norman.

$175,000

Capital Fund - Reed Avenue Curb and Gutter Project

Proposed amendment for improvements along the west side of Reeve Avenue, with discussion on alternate funding for design.

$145,000

Capital Fund - Regional Transit Authority (RTA) Request

Increased request for FYE 24, up from $182,000.

$348,000

Norman Ford Fund - Young Family Athletic Center & Adult Wellness Center

Funds de-appropriated from the current fiscal year and re-appropriated for these projects in FYE 24 to ensure a positive ending fund balance.

Parkland and Development Fund - Reeves Park Maintenance Building Phase One

New project included as part of future master plan phases to improve maintenance efficiency for baseball and softball fields and to replace an old maintenance building.

Coming Up

Watch For

  • I-35 Corridor study
  • Possible impacts of the Access Oklahoma Turnpike plan with public transportation
  • Regional Transit Authority (RTA) developments
  • New traffic signals on state highways and City arterials
  • City's Fleet replacement
  • Fleet facility renovation
  • I.T. infrastructure and Microsoft system upgrades
  • Bridge Replacements and major maintenance
  • Stormwater infrastructure
  • Upgrades and repairs needed at the fueling facility
  • Sidewalk gaps
  • Escalating construction costs
  • Multiple master plan updates
  • Traffic Management Center and staffing
  • Possible Redevelopment of the land with the Griffin Hospital (TIF District possibility)
  • Possibility of a new UNP Arena (TIF District possibility)
  • OU airport expansion (potential land acquisition/agreements)
  • Future remodel and replacement of Building B (scope pending Public Safety study)
  • Oversized emergency vehicle storage facility at the ECOC

Agenda Summary

Discussion regarding the fiscal year ending 2024 Capital Improvements program budget

Presentation and discussion of the final proposed Capital Improvements Program budget for FY2024 and the Capital Improvements Plan for FY25-28, including updates on funded projects, proposed new projects, and midpoint evaluations.

Information Only