Meeting Summary

TL;DR

The City Council held a special meeting to discuss the Norman Nature Park design. The conceptual design, budget, and timeline were presented, focusing on nature-themed play areas, enhanced stormwater capacity, and ADA accessibility. The Council approved moving forward with the design and permitting process, with construction anticipated to begin in August 2024 and the park opening by early summer 2025.

Key Decisions & Votes

Norman Nature Park Design Approval

29:50

The City Council approved moving forward with the conceptual design and the necessary permitting processes for the Norman Nature Park. This includes developing construction documents and securing approvals from the Core of Engineers and the city's stormwater department.

Approved

Financial Matters

Norman Nature Park Project Budget

The project has an initial allocation of $1.5 million, with approximately $1.25 million remaining for construction after design and surveying fees. The current construction estimate is $1.2 million, including a 7.5% design contingency.

$1.5 million

Coming Up

Deadlines

  • Billboard removal: February 2025
  • Park opening: Early summer/late spring 2025

Watch For

  • Core of Engineers permit decision for the Nature Park
  • City of Norman stormwater permit for the Nature Park
  • Bid packages and construction drawings for the Nature Park
  • Council approval of construction contract for the Nature Park
  • Potential future addition of a bridge across the creek

Agenda Summary

Discussion regarding the Norman Nature Park design

Presentation and discussion of the conceptual design for the Norman Nature Park, including proposed features, accessibility, budget, and project schedule.

Approved